By: Derek Hawkins//October 26, 2017//
WI Court of Appeals – District II
Case Name: Ostrenga Excavating, Inc. v. Cleveland Construction, Inc., et al.
Case No.: 2016AP7
Officials: Neubauer, C.J., Gundrum and Hagedorn, JJ
Focus: Damages and Breach of Contract Claim
Cleveland Construction, Inc., (CCI) appeals from a judgment awarding Ostrenga Excavating, Inc., $55,276. Ostrenga cross appeals from the judgment, conditionally challenging the circuit court’s determination on summary judgment if we reverse the judgment entered after trial. We conclude that the jury’s verdict awarding CCI only $48,724 in damages is unsupported by any credible evidence. The absence of credible evidence to support the jury’s verdict on this issue carried through to additional questions addressing Ostrenga’s damages. Therefore, based on the current record and posture of this appeal, we order a new trial on damages. In addition, we conclude that the circuit court properly awarded CCI partial summary judgment on the implied-in-fact contractual issue, but erred in dismissing Ostrenga’s misrepresentation claims based on the economic loss doctrine, and did not err in granting Ostrenga leave to amend its complaint to add a breach of contract claim.